Projects

Sinking Fund Projects


Project & Progress Costs Dates Contractors
ACS
Bus
Garage
Transformer replacement Actual:
$13,775.00
Completed:
8/13/24
RCI Electrical Contracting
Baseball field press box electricity addition Actual:
$18,981.91
Completed:
8/7/24
RCI Electrical Contracting


Almont
High
School
Exhaust fan replacement
  • RFP process started on 10/9/24, ending 10/25/24
  • Board approved Thumb Cooling and Heating on 12/10/24
  • Fans are on order, should be in by end of January/beginning of February
Actual:
$29,260.00

Thumb Cooling and Heating
Fire panel replacement
  • RFP process started on 10/9/24, ending 10/25/24
  • Board approved Shoreview Electric on 12/10/24
  • Working on scheduling installation
Actual:
$161,877.12

Shoreview Electric
Select interior and exterior doors
  • RFP process started on 10/9/24, ending 10/25/24
  • Work will depend on product availability and weather
  • Potential savings and more stringent guidelines prompted a repost of the bid which was due on 1/17/25
  • Currently evaluating bids that were received



Rekeying the district
  • Key blanks and cylinders are being ordered by the district, will bid out the labor



Sink hole in receiving area Actual:
$5,800.00 YSI,
$1,375.00 TCPR
Completed:
8/19/24
Yard Services Inc.,
Tri County Power Rodding
Weight room heat, bearing assembly replacement Actual:
$6,217.00
Completed:
7/22/24
Limbach
Main gym and aux gym floor refinishing Actual:
$4,901.00
Completed:
7/19/24
Axium Services
Tennis courts Actual:
$11,100.00 UA,
$1,325.00 YSI,
$3.223.27 HD
Completed Ultimate Asphalt,
Yard Services Inc.,
Home Depot
Bleacher repairs, main and aux Actual:
$6,022.00,
$5,986.00
Completed:
10/10/24

Replacing 7 science lab faucets Actual:
$5,303.00
Completed:
11/8/24
Limbach
Old concessions shingle and roof vent repairs Actual:
$4,950.00
Completed:
10/24/24
Royal Roofing
Bleacher end curtains Actual:
$3,387.69
Completed:
11/9/24
Side Effects Inc.
Auditorium AC replacement Actual:
$24,815.00
Completed:
11/20/24
Limbach
Stadium bleacher repairs Actual:
$15,088.00
Completed American Athletix


Almont
Middle
School
Select interior and exterior doors
  • RFP process started on 10/9/24, ending 10/25/24
  • Work will depend on product availability and weather
  • Potential savings and more stringent guidelines prompted a repost of the bid which was due on 1/17/25
  • Currently evaluating bids that were received



Refinish gym floor
  • RFP process started on 10/9/24, ending 10/25/24
  • Will be a summer 2025 project
Actual:
$23,900.00

Varsity Flooring
Fob install at door #2 Actual:
$3,810.04
Completed:
1/31/25
Building Security and Automation
Rekeying the district
  • Key blanks and cylinders are being ordered by the district, will bid out the labor



Art classroom sink, paint interceptor Actual:
$1,769.00
Completed:
7/16/24
Limbach
Kitchen touch-free washing station replacement Actual:
$4,724.00
Completed:
7/16/24
Limbach
Science room chemical drain pit Actual:
$3,850.00
Completed:
8/19/24
Tri County Power Rodding
Overhead sprinkler repairs Actual:
$4,556.51
Completed:
6/24
Cintas Fire Protection
Safety sidewalk at west lot/entrance Actual:
$15,924.00 MCC (sidewalk),
$7,509.36
Completed:
11/4/24
Midwest Commercial Construction,
TMT Parking
Bleacher end curtains Actual:
$s6,776.33
Completed:
11/9/24
Side Effects Inc.
Bleacher repairs Actual:
$2,664.00
Completed:
11/10/24
American Athletix
Kitchen touch-free washing station replacement Actual:
$4,724.00
Completed:
11/27/24
Limbach


Orchard
Primary
School
Replace select classroom windows
  • RFP process started on 10/9/24, ending 10/25/24
  • Will be a summer 2025 project
  • Securing materials and scheduling
  • Board approved Trenko Glass on 12/18/24
  • Windows are ordered, 30% down payment ($31,104.00) to cover initial window purchase
Actual:
$103,680.00

Trenko Glass
Rekeying the district
  • Key blanks and cylinders are being ordered by the district, will bid out the labor



Playground equipment Actual:
$4,250.00 GLR,
$800.00 YSI
Completed Great Lakes Recreation,
Yard Services Inc.
Boiler repairs Actual:
$3,148.00
Completed Macomb Group
Fix the slope for the storm drain/spillway of bus loop Actual:
$1,850.00
Completed:
10/7/24
Yard Services Inc.
Plumbing repair in 2 classrooms Actual:
$3,500.00
Completed:
11/1/24
Limbach
Sidewalk repair, south ADA entrance – south lot Estimated:
$9,291.00 Actual:
$9,791.00
Completed:
11/1/24
Midwest Commercial Construction
Playground equipment repair Actual:
$8,726.00
Completed Great Lakes Recreation,
Yard Services Inc.
Replace classroom drinking fountain shutoffs and supply lines Actual:
$3,000.00 Limbach,
$282.93 supplies
Completed Limbach,
supplies purchased by district


ACS
Disrict-wide
Tree removal, practice field treeline Actual:
$5,625.00
Completed:
12/7/24
Kappen Tree Service